Successful project completion in the Tyrolean high mountains
In the first project report, we already provided detailed information about Kremsmüller’s high-altitude construction site in Schranbach in the Tyrolean Sulztal valley. Kremsmüller supplied central plant components for the Kühtai storage power plant of Tiroler Wasserkraft AG (TIWAG). A sustainable project that Kremsmüller has successfully completed.
Find out more about the challenges, work processes, and project completion in the new YouTube video.

Custom-Designed Reactor Solution
For a customer in the chemical industry, the Austrian family-owned company Kremsmüller manufactured what is known as an oxidation reactor. For this project, Kremsmüller assumed

Two Steam Storage Facilities for a Green Future
With the delivery of two massive steam storage tanks, Kremsmüller recently contributed to what is currently likely Austria’s largest climate protection program: voestalpine in Linz

Kremsmüller is building the core component of the steam-water cycle
At its site in St. Johann in Tirol, the internationally active wood-based materials manufacturer Egger is constructing a new boiler plant to generate renewable energy

Process data must be verified
Process data must be verified Process verification is essential before implementing new processes. Kremsmüller helps customers validate evaporation and drying concepts in the pilot plant

Kremsmüller in action for voestalpine
Project for voestalpine in Linz Kremsmüller is carrying out Lot 3, “Balance of Plant,” for voestalpine Stahl GmbH at Power Plant Unit 8 in Linz—from